Phase F: Migration Planning
Finalize the roadmap and produce a costed, sequenced Implementation and Migration Plan agreed with the wider portfolio.
About this phase
Phase F finalizes the Architecture Roadmap and turns the outline plan from Phase E into a detailed Implementation and Migration Plan, coordinated with the enterprise's portfolio, program, and project management frameworks.
The phase assesses the business value, cost, and risk of each work package; prioritizes migration projects; assigns resources and timings; and confirms the plan with the stakeholders who will fund and deliver it. Nothing should be in the plan that the delivery organization has not agreed to.
Phase F also closes the architecture development cycle for this iteration: the Architecture Definition Document, Requirements Specification, and Roadmap are completed, lessons learned are documented, and the baton passes to implementation governance in Phase G.
Objectives
- Finalize the Architecture Roadmap and the supporting Implementation and Migration Plan.
- Ensure that the Implementation and Migration Plan is coordinated with the enterprise's approach to managing and implementing change in the enterprise's overall change portfolio.
- Ensure that the business value and cost of work packages and Transition Architectures is understood by key stakeholders.
Steps in this phase
0/7 · 0%Key inputs
- Request for Architecture Work, Statement of Architecture Work, Architecture Vision
- Communications Plan and Capability Assessment
- Organizational Model for Enterprise Architecture and Tailored Architecture Framework
- Governance models and frameworks
- Architecture Repository
- Draft Architecture Definition Document, including Transition Architectures
- Draft Architecture Requirements Specification
- Architecture Roadmap v0.1 and Implementation and Migration Plan v0.1 (from Phase E)
Key outputs
- Implementation and Migration Plan v1.0 (detailed, approved) — including the Implementation and Migration Strategy and project charters as appropriate
- Finalized Architecture Definition Document — including finalized Transition Architectures
- Finalized Architecture Requirements Specification
- Finalized Architecture Roadmap
- Reusable Architecture Building Blocks stored to the Architecture Repository
- Requests for Architecture Work for a new iteration of the ADM cycle (if any)
- Implementation Governance Model (produced with Phase G in view)
- Change Requests for the Architecture Capability arising from lessons learned
Worked example — Meridian Retail Group
Generated sample documents for a fictional company, showing what this phase consumes and produces. They are illustrative study aids, not templates from the standard.
Example inputs
example inputDeliverablefrom PreliminaryThe document from the sponsoring organization that triggers an ADM cycle — the key handoff from the Preliminary Phase into Phase A.
Request for Architecture Work
Sponsoring organization: Meridian Retail Group — Office of the COO Date: 2 April 2026 Reference: RAW-2026-001 Addressed to: Architecture Board (submitted via the Lead Architect)
Organization sponsors
Chief Operating Officer (business sponsor); Chief Information Officer (executive sponsor for architecture).
Mission statement
Deliver the "One Meridian" unified customer experience: any customer, recognized in any channel, served from a single view of orders, inventory, and preferences.
Business goals and changes
- Increase repeat-purchase rate from 31% to 40% within 24 months
- Enable buy-online-pickup-in-store (BOPIS) in all 240 stores
- Consolidate 4 customer databases into a governed single customer view
- Reduce integration spend by 20%
Strategic plans
Responds to the One Meridian strategy (FY26–FY28) and Board Directive 26-04. Goals map to drivers DRV-01 to DRV-04 in the Driver/Goal/Objective catalog.
Time limits
- Architecture definition (Target Architecture and roadmap) approved before the 1 Nov 2026 peak trading freeze
- First Transition Architecture in production before the FY27 peak freeze
Changes in the business environment
Competitors now offer click-and-collect as standard; digital revenue at 26% and rising; POS v9 reaches end of life in 2027.
Organizational constraints
- Peak trading freeze: no production change 1 Nov – 15 Jan
- Franchise stores operate their own POS until contract renewal (FY27)
Financial constraints
Indicative program envelope of $18M over 2 years, subject to Investment Committee approval per tranche.
External and business constraints
- GDPR and PCI-DSS compliance mandatory
- 3PL logistics contract fixes EDI message formats until 2027
Current business system description
Channel-based operating model: Digital Commerce, Store Operations, and Customer Care each run their own customer processes and service standards.
Current systems description
4 customer databases, 3 order management systems, in-store POS (v9, EOL 2027), monolithic e-commerce platform, nightly-batch warehouse integration.
Developing organization and resources available
Meridian EA team (Lead Architect plus 4 domain architects), working under the Tailored Architecture Framework v1.0 and Architecture Principles v1.0. Business subject-matter experts released for up to 2 days per week during Phases B–D.
Success criteria
An approved Target Architecture and Implementation and Migration Plan for the One Meridian program, with the first Transition Architecture delivered before the FY27 peak trading freeze.
Submitted by: COO, 2 April 2026 · Accepted for Phase A: Architecture Board, 9 April 2026
Example outputs
example outputDeliverableThe finalized, costed, and sequenced plan integrated with the enterprise portfolio.
Implementation and Migration Plan v1.0 — One Meridian (excerpt)
Approved: Architecture Board + Investment Committee, 28 Oct 2026 Owner: J. Okafor (Lead Architect) with Head of PMO · Supersedes: v0.1 (Phase E)
1. Implementation and Migration Strategy (confirmed)
Evolutionary change through three Transition Architectures (TA-0, TA-1, TA-2) to the FY28 Target. Each project is chartered through the PMO (charters PC-P1 to PC-P7) and runs inside the existing stage-gate model. No production change in the peak freeze (1 Nov – 15 Jan).
2. Project portfolio and schedule
| Project (delivery vehicle) | Work packages | Start | End | Cost est. | Business value (score /25) | Priority |
|---|---|---|---|---|---|---|
| P1 Platform Foundation (program: Digital Core) | WP-08, WP-11 | Nov 2026* | Feb 2027 | $2.8M | 14 (enabler) | 1 |
| P2 Integration Migration wave 1 | WP-06a | Jan 2027 | Mar 2027 | $0.9M | 12 | 2 |
| P3 Customer Foundation | WP-10, WP-01, WP-04 | Feb 2027 | Jun 2027 | $4.6M | 21 | 1 |
| P4 One-step Returns | WP-03 | May 2027 | Jul 2027 | $0.8M | 18 | 2 |
| P5 Commerce Core | WP-05, WP-02, WP-04b | Apr 2027 | Oct 2027 | $5.1M | 23 | 1 |
| P6 POS Pilot (20 stores) | WP-07a | Jun 2027 | Oct 2027 | $1.7M | 15 | 2 |
| P7 POS Rollout + decommission | WP-07b, WP-06b | Jan 2028 | Sep 2028 | $2.4M | 16 | 3 |
* P1 cloud-side work only during freeze — no store or production-commerce change.
P2 starts after the freeze lifts (18 Jan 2027). P4 goes live with TA-1 on 28 Jun 2027; July is hypercare and completion of store training. WP-09 (store network and PCI segmentation) is delivered by the Store Estate Refit program from its existing capex line and is tracked here as an external dependency.
3. Funding tranches
| Tranche | Projects | Value | Release condition |
|---|---|---|---|
| T1 | P1–P4 | $9.1M | Approved 28 Oct 2026 |
| T2 | P5–P6 | $6.8M | TA-1 acceptance evidenced (Jun 2027) |
| T3 | P7 | $2.4M | TA-2 acceptance evidenced (Oct 2027) |
Total $18.3M against the indicative $18M envelope. The Investment Committee accepted the $0.3M variance, offset by avoiding the FY27 DC hardware refresh.
4. Resource and dependency notes
- Store field force capped at 40 refits/month → P7 rollout wave plan of 6 months
- Data migration (P3) gated on Data Governance Council survivorship sign-off
- P5 cannot enter production before TA-0 platform acceptance (P1 exit criteria)
- P5 and P6 share the SI partner; P6 uses a separate POS vendor team
- Jul–Oct 2027 field-force load: 30 network refits + 5 POS pilot stores a month, within the cap
5. Key risks (validated in step 4)
| Risk | Rating | Mitigation | Owner |
|---|---|---|---|
| Customer data migration quality (REQ-D-01) | High | Two trial migrations before cutover; council sign-off | Customer Data Steward |
| P5 slips into the 2027 peak freeze | Medium | Go/no-go on 4 Oct 2027; fallback is web-only Order Hub | P5 Program Director |
| Franchise renewal delays P7 franchise waves | Medium | Franchise stores scheduled in last wave | Store Ops Director |
6. Benefits realization
Benefit owners and measures agreed per project; tracked quarterly by the Investment Committee (e.g., P5: BOPIS revenue/store/week; P3: duplicate-profile rate, care handle time).
7. Lessons learned (cycle closure)
- Engage franchise partners in Phase A next cycle — late discovery of contract constraints reshaped POS sequencing.
- Consolidated gap matrix maintained continuously (not only in Phase E) would have saved rework between Phases C and D.
See the lessons-learned record for the resulting Change Requests.
Study tips & key concepts
- Phase E creates the initial roadmap and outline plan; Phase F costs it, sequences it, and gets it agreed — 'finalize and coordinate' are the Phase F verbs.
- The Implementation and Migration Plan must fit the enterprise's existing portfolio/program/project frameworks — architecture doesn't get its own parallel delivery machinery.
- Business Value Assessment: a technique to position each project by value vs. risk (often drawn as a matrix) with agreed measures reviewed periodically.
- The Architecture Definition Increments table shows which deliverables/state each project reaches per Transition Architecture — a classic Phase F artifact.
- Phase F ends the 'architecture development' half of the cycle; deliverables are finalized here and governed through implementation in Phase G.